Town
to begin using sewer rehab money changes
By Richard D. L. Fulton
News Editor
EMMITSBURG,
Md. – The town could begin drawing down money from an
approved $656,107 community development block grant (CDBG) this
month.
The town
was awarded the grant in December 2005 to resolve both a long
history of sewage spills apparently originating from a missing
valve in the collection system, and to extend sewer service
to the new Emmitsburg Glass facility on Creamery Road.
In addition,
the funds would be used to make modifications at the sewer
plant to accommodate improvements made along the collection
system itself.
Two bids
to begin the collection system work and glass company site
connection were approved at the Dec. 5 town meeting.
JHG Contractors,
Frederick, was awarded a bid of $67,945 to begin work on the
installation of a three-inch wastewater forced main, as well
as a bid of $114,000 for the installation of an eight-inch
water main.
Rejected
was a $735,105 bid from W. F. Delauter & Son, Thurmont,
for a forced wastewater main replacement and related work.
That bid represented a 163 percent increase over the estimated
cost of the project.
Work
on the approved projects, according to Town Manager David
Haller, could be completed in 90 to 100 days, although the
contracts would allow 240 days for completion. The work could
begin relatively soon, he said. Town spokeswoman Patricia
Feeser told The Dispatch work could begin during
the first week in February.
However,
proposed expenditures have to go through various levels of
state approval. The total grant amount is reserved for the
town at the state level, and the town will draw-down on the
allotment by submitting project-related bills as work progresses.
Regarding
approval to spend money, Feeser said, “You have to go
through all the steps. There are environmental surveys that
have to be done, a lot of different steps.”
The forced
water main phase of the project, whose bid the commissioners
had rejected on Dec. 5, will be re-bid, but the papers to
do so have not yet been prepared.
The wastewater
collection system has been responsible for the spillage of
hundreds of thousands of gallons over the years, the main
culprit apparently being a missing valve which may never have
been installed. The valve would have acted as a “brake”
where the high-pressure wastewater line coming from town met
the gravity-feed line going to the treatment plant.
The proposed
overhaul would remedy the spillage problem by switching to
an all-pressure collection system, and making adjustments
at the treatment plant to receive the high pressure inflow
of sewage.